What is the difference between the actual price of an input and its standard price multiplied by the actual amount of the input purchased?

labor efficiency variance

the difference between the actual hours taken to complete a task and the standard hours allowed for the actual output, multiplied by the standard hourly labor rate

he difference between the actual hourly labor rate and the standard rate, multiplied by the number of hours worked during the period

the difference between the actual unit price paid for an item and the standard price, multiplied by the quantity purchased

materials quantity variance

the difference between the actual quantity of materials used in production and the standard quantity allowed for the actual output, multiplied by the standard price per unit of materials

a variance that is computed by taking the difference between the actual price and the standard price and multiplying the result by the actual quantity of the input

a variance that is computed by taking the difference between the actual quantity of the input used and the amount of the input that should have been used for the actual level of output and multiplying the result by the standard price of the input

a detailed listing of the standard amounts of inputs and their costs that are required to produce one unit of a specific product

the standard quantity allowed of an input per unit of a specific product, multiplied by the standard price of the input

the time that should have been taken to complete the period's output. It is computed by multiplying the actual number of units produced by the standard hours per unit

the amount of direct labor time that should be required to complete a single unit of product, including allowances for breaks, machine downtime, cleanup, rejects, and other normal inefficiencies

standard quantity per unit

the amount of an input that should be required to complete a single unit of product, including allowances for normal waste, spoilage, rejects, and other normal inefficienc9es

the price that should be paid for an input

standard quantity allowed

the amount of an input that should have been used to complete the period's actual output. It is computed by multiplying the actual number of units produced by the standard quantity per unit

the labor rate that should be incurred per hour of labor time, including employment taxes and fringe benefits

variable overhead efficiency variance

the difference between the actual level of activity (direct labor-hours, machine-hours, or some other base) and the standard activity allowed, multiplied by the variable part of the predetermined overhead rate

variable overhead rate variance

the difference between the actual variable overhead cost incurred during a period and the standard cost that should have been incurred based on the actual activity of the period

In any manufacturing company Purchase Price Variance (PPV) Forecasting is an essential tool for understanding how price changes in purchased materials affect future Cost of Goods Sold and Gross Margin.

This helps business stakeholders to make more informed pricing decisions and finance functions to give more accurate forward-looking statements on overall future profitability.

In this article, we'll explain what PPV is, how it's used in budgeting and performance measurement, and how to forecast it. 

How to caluculate PPV? 

Purchase Price Variance is the difference between the Actual Price paid to buy an item and the Standard Price, multiplied by the Actual Quantity of units purchased. Here is the formula:

Purchase Price Variance = (Actual Price – Standard Price) x Actual Quantity


PPV in budgeting

Direct material purchases can add up to 70% of all the costs in manufacturing companies.

Hence, budgeting and following up on material prices is a key job of any finance function in this type of business.

When a financial budget is created, the exact price of materials is unknown. So, the best estimate needs to be used. In accounting, this best estimate price is called Standard Price.

After the budgeted costs are realized, companies have an accurate measure of the Actual Price and Actual Quantity of units bought.

What PPV means

A Positive Variance means the actual costs are higher than the budgeted.

A Negative Variance means that costs are lower.

Thus, positive variance can usually be considered a bad thing and negative variance a good thing.

Interested in diving into more procurement insights? Check out our guide Spend Analysis 101

What is the difference between the actual price of an input and its standard price multiplied by the actual amount of the input purchased?

PPV in performance measurements

PPV can be used to quantify the efficiency of a company’s procurement function.

Negative PPV is considered savings and thus good performance from the procurement organization.

But this is a very simplistic approach as commodity price volatility is often outside the control of buyers.

In the worst cases, PPV as a performance measure can lead to politics around Standard Price setting instead of providing a motivating KPI for the procurement team.

PPV in financial planning

On the other hand, PPV is valuable for financial planning.

It explains how material price changes have affected your gross margin compared to your budget.

This is a key component in understanding the development of overall business profitability and thus a vital financial performance indicator.

And it is usually readily available from your finance systems where PPV calculations should happen automatically.

What is the difference between the actual price of an input and its standard price multiplied by the actual amount of the input purchased?
What is the difference between the actual price of an input and its standard price multiplied by the actual amount of the input purchased?

Forecasting Purchase Price Variance 

PPV is a historical indicator telling you what has happened in the past. Imagine, however, how powerful a forward-looking PPV indicator would be.

Enter Forecasted PPV, a performance indicator that can highlight the future risk to your gross margin and overall profitability.

The math needed to calculate Forecasted PPV is straightforward and similar to the Realized PPV formula:

Forecasted PPV = (Forecasted Price – Standard Price) x Forecasted Quantity

With Forecasted PPV business units gain the much-needed visibility on how material price changes are expected to erode gross margins.

You can proactively take needed actions to protect those margins. Finance teams can confidently adjust their forecasts with forward-looking statements that explain the effect of material price changes.

What is the difference between the actual price of an input and its standard price multiplied by the actual amount of the input purchased?

What is the difference between the actual price of an input and its standard price multiplied by the actual amount of the input purchased?
 

Challenges of forecasting PPV

So, if Forecasted PPV is such a great performance indicator and simple to calculate, why are not all companies using it?

The problem is that Forecasted PPV can’t be automatically calculated by your ERP or finance system.

Your SAP contains your Standard Prices, but coming up with reliable data on Forecasted Prices and Quantities is a much more complex exercise.

Forecasted quantities should be based on expected market demand (and production volumes), but often this information is not accurate or available for all business units and regions.

The data you need

Quantity forecasts are usually the result of combining

  • Data from demand planning and MRP systems
  • Extrapolated historical quantities and previous forecasts
  • Manual entry and adjustment by persons who best understand demand

Forecasted prices can come from purchasing systems with long enough visibility to contracted prices. Still, procurement people need to manually estimate at least the key materials based on their view of the supply market and with the help of cost structure models.

In a large enterprise with multiple source systems for forecast data, tens of thousands of material numbers to be forecasted and a score of plants and business units involved in the process.

Building and maintaining a regular Purchase Price Variance Forecast is not a task to be taken lightly! 

Sievo Materials Forecasting – PPV Forecasting made easy 

Sievo’s Materials Forecasting is a purpose-built solution for all purchase-related forecasting needs. And if you are looking for a system for Purchase Price Variance Forecasting, we got you covered.

But don’t take our word for it. Hear what Chris from Becton Dickinson has to say about Sievo Materials Forecasting:

Intrigued? Request a personalized demonstration from our website.

Read More

Working capital optimization through payment terms

Financial managers are constantly being asked to do more with less. It is..

Savings & Finance,

3 ways to tackle commodity price fluctuations and volatility

In procurement, a commodity is a raw or semi-processed material used to..

Savings & Finance,

Everything you need to know about Procurement savings

The main goal of procurement is to ensure products and services are bought..

Savings & Finance,

6 tips to improve your indirect spend management

Indirect procurement spend is the sourcing of goods and services not..

Category Management

What is spend management and why is it important?

The last few years have put the maturity and competencies of procurement..

Spend Analysis

Leveraging spend analytics in strategic sourcing

Strategic sourcing has a vital role to play in supply chain management and..

Data & Analytics

Why onshoring supports your sustainable procurement agenda

In the procurement world, offshoring is the relocation of production,..

Sustainability & Diversity

Modern Slavery in Procurement

Modern slavery can be defined as the recruitment, movement, harboring or..

Sustainability & Diversity

Never miss news from Sievo

Get updates straight to your inbox

What is the difference between the actual and standard unit price of an input multiplied by the number of inputs used?

Answer and Explanation:.

What is the difference between the actual price and the standard price multiplied by the actual quantity of materials purchased?

Hence material price variance is the difference between standard price and actual price multiplied by actual quantity.

When the standard price is higher than the actual price the materials price variance is?

Variance is unfavorable because the actual price of $1.20 is higher than the expected (budgeted) price of $1. $(21,000) favorable materials quantity variance = $399,000 – $420,000. ... Learning Objective..

What is price purchase variance?

Purchase price variance (PPV) is the difference between the actual purchased price of an item and a standard (or baseline) purchase price of that same item. It is assumed that the product quality is the same and that the quantity of the items purchased and the speed of delivery does not impact the purchased price.